CASE STUDY no. 1

See Reality Earlier

01.jpg

KEY TAKEAWAY

Identifying constraints before they become delays

02.jpg
55a6b981-35c3-424d-9602-122a53d6c42c~1.jpg
02.jpg
cdb9a56c-f5cf-497a-8e5d-bae2519dced4~1.jpg
02.jpg
20230628_085520775_iOS.heic

THE CHALLENGE
Work was regularly starting without full readiness. Access, information and prerequisite issues were discovered late, causing stoppages and resequencing.

​

WHAT WE DID

  • Introduced Lean lookahead planning focused on makeready, not dates

  • Used digital visual management to make constraints visible

  • Mentored teams to test readiness before committing

​

WHAT IMPROVED

  • Constraints surfaced weeks earlier instead of during execution

  • Fewer aborted starts and last minute changes

  • Improved confidence in lookahead plans

  • More open discussion of “not ready” work

​

​

LeanActivity.png

THE OUTCOME

Teams moved from reacting to problems to anticipating them, improving stability and trust in planning.