CASE STUDY no. 1
See Reality Earlier

KEY TAKEAWAY
Identifying constraints before they become delays






THE CHALLENGE
Work was regularly starting without full readiness. Access, information and prerequisite issues were discovered late, causing stoppages and resequencing.
​
WHAT WE DID
-
Introduced Lean lookahead planning focused on makeready, not dates
-
Used digital visual management to make constraints visible
-
Mentored teams to test readiness before committing
​
WHAT IMPROVED
-
Constraints surfaced weeks earlier instead of during execution
-
Fewer aborted starts and last minute changes
-
Improved confidence in lookahead plans
-
More open discussion of “not ready” work
​
​

THE OUTCOME
Teams moved from reacting to problems to anticipating them, improving stability and trust in planning.