CASE STUDY no. 2

Improve delivery reliability

088c6435-32d5-4e74-a8b4-52baf7e278a0~1.jpg

KEY TAKEAWAY

From optimistic plans to reliable commitments

3e7f9bec-6998-4738-8c15-afff0cc560fc~1.jpg
02.jpg
3e7f9bec-6998-4738-8c15-afff0cc560fc~1.jpg
3e7f9bec-6998-4738-8c15-afff0cc560fc~1.jpg
02.jpg
5d649ce5-205c-416e-81f5-81e4ab4e30de copy.jpg
3e7f9bec-6998-4738-8c15-afff0cc560fc~1.jpg
02.jpg
09.jpg

THE CHALLENGE

Weekly plans were unreliable. Planning meetings focused on explaining missed work rather than improving flow.

​

WHAT WE DID

  • Implemented the Last Planner System® as a production control system

  • Reframed weekly planning as a commitment conversation

  • Digitally supported clearer task definition and readiness checks

  • Coached leaders and supervisors in Lean planning behaviours

​

WHAT IMRPOVED (metricslight)

  • Planned Percent Complete (PPC) improved materially over time

  • Fewer tasks released prematurely

  • Better quality task definitions

  • Planning meetings became shorter, more focused and more collaborative

​

CS2Image.png

THE OUTCOME

Commitments became more realistic, and delivery reliability improved without accelerating the programme.