CASE STUDY no. 2
Improve delivery reliability

KEY TAKEAWAY
From optimistic plans to reliable commitments









THE CHALLENGE
Weekly plans were unreliable. Planning meetings focused on explaining missed work rather than improving flow.
​
WHAT WE DID
-
Implemented the Last Planner System® as a production control system
-
Reframed weekly planning as a commitment conversation
-
Digitally supported clearer task definition and readiness checks
-
Coached leaders and supervisors in Lean planning behaviours
​
WHAT IMRPOVED (metricslight)
-
Planned Percent Complete (PPC) improved materially over time
-
Fewer tasks released prematurely
-
Better quality task definitions
-
Planning meetings became shorter, more focused and more collaborative
​

THE OUTCOME
Commitments became more realistic, and delivery reliability improved without accelerating the programme.